Site Induction

Roofing Works & CFR Sites

Read all sections carefully before signing.

0 of 9 sections ticked.

You are offline

You are reading the standard CFR induction. You can complete and sign it now — it will be sent to the office when you get signal.

1. Welcome & Induction Overview

Welcome to the site. This induction covers safety requirements, emergency procedures, and environmental responsibilities for all personnel working on roofing projects.

2. Site Rules & General Safety

  • Follow all site signage and instructions from supervisors
  • No running on site
  • Report all hazards immediately
  • Keep work areas clean and free of trip hazards

3. Personal Protective Equipment (PPE)

Mandatory PPE:

  • Hard hat
  • High-visibility vest or jacket
  • Steel toe-capped safety boots
  • Gloves suitable for roofing tasks
  • Eye protection when cutting or drilling
  • Harness and fall protection equipment when working at height if edge protection is not in place

4. Working at Height

  • Use only certified scaffolding, mobile towers, or MEWPs
  • Always use fall protection systems
  • Never work on fragile roofs without proper edge protection
  • Two-person rule for high-risk roof work

5. First Aid & Emergency Procedures

  • First aid kit located at the site welfare unit
  • First aider on site — ask your supervisor
  • In case of emergency, call 999
  • Assembly point is located at the site entrance

6. Environmental Considerations

  • Prevent debris and materials from entering watercourses or drains
  • Dispose of waste materials in designated skips
  • Minimise dust and noise where possible
  • Protect existing vegetation and trees around the site

7. Hazards Specific to Roofing

  • Fragile roof materials
  • Slippery surfaces when wet
  • Falling tools and materials
  • Manual handling of heavy roofing sheets
  • Exposure to weather conditions

8. COSHH – Control of Substances Hazardous to Health

  • All hazardous substances must be assessed before use
  • Use only approved products on site
  • Follow the COSHH assessment and safe systems of work
  • Store chemicals in designated, labelled containers
  • Use appropriate PPE when handling adhesives, solvents, or coatings

9. Hot Works Procedures

  • Hot works require a daily hot work permit
  • Must sign in and out on the permit
  • Keep a fire watch for at least 60 minutes (increased at times due to site specifics) after works finish
  • Use safety torch in designated areas shown on the site plan, abiding by the Safe to Torch site plan
  • Fire extinguisher must be immediately available during all hot works — 2 extinguishers per gas torch

Operative Declaration

By signing below, I confirm that I have read, understood, and agree to comply with all sections of this site induction.

Operative's Signature *

Not signed yet

Induction Conducted By

Conductor's Signature *

Not signed yet